AIMS5.0 asks when a chip furnace should wait

Generated scheduling rules weigh delivery delays and electricity costs against the time limits imposed by wafer processing.

Starting a partly filled furnace keeps wafers moving; waiting may fill the batch or reach a cheaper electricity period. AIMS5.0’s 22 October update describes genetic programming that learns dispatching rules for this choice: candidate formulas are tested and recombined, with better-performing versions retained.[1][2]

A related 29 May paper by Daniel Schorn and Lars Mönch models two processing stages. It balances electricity cost with lateness weighted by each job’s priority. Wafers have time limits between operations because excessive delays can cause oxidation or contamination. Searching for rules happens offline; applying them is comparatively quick.[2]

Consider this invented planning example, not a project result. Two compatible lots fit one furnace run. Lot A is ready at 10:00 and must start by 11:00; lot B is ready at 10:45. The tariff falls at 10:30. Ignore warm-up changes and other work in the queue.

At a glance

Three possible start times

Three possible start times
ChoiceWhat happens
Start at 10:00A proceeds alone before the lower tariff begins.
Wait until 10:45A and B fit together; A still meets its latest start.
Wait until 11:15Both are ready, but A’s processing limit is missed.

The paper tests generated scheduling problems, rather than reporting a measured factory electricity saving. Its heuristics can leave time-limit violations, and it assumes a specified tariff pattern. Cheaper operation alone cannot establish that fewer kilowatt-hours were used.[2]