OVHcloud’s AI plans start with connected power

Electrical headroom creates room to expand. Servers, cooling and services determine what it can become.

OVHcloud’s 20 October results report 250 MW of connected power and 140 MW in operation. The 110 MW difference gives it room to grow without building new sites, the company says.[1]

That figure describes connected power, not installed GPU capacity. In his accompanying letter, chief executive Octave Klaba describes adapting liquid cooling to newer GPUs and a supply chain able to respond to customer demand within days.[2]

The hardware between power and useful work

OVHcloud’s October 2025 Smart Datacenter announcement shows the physical chain involved. Waterblocks on processors carry heat into a closed water circuit. A cooling distribution unit serves several rack rows, with sensors monitoring pressure, speed and temperature. The outside cooler then rejects the heat.[3]

That design lets software adjust pumps, fans and valves as workloads and surroundings change. Its AI can choose different trade-offs between water and electricity use. The useful capacity of a site depends on this complete installation: servers, water circuits and outdoor heat removal working together.[3]

Hardware still requires investment. OVHcloud says it bought €49.5 million of memory and disk components in advance for its 2027 financial year.[1]

OVHcloud says 2027 will be the deployment phase of its redefined AI strategy. It plans to explain more at its 19 November AI summit.[1]